The element
- Requirement
The community knows how much electricity each machine draws at idle and at load, keeps its computing inside its energy budget, protects it from power cuts with an uninterruptible supply installed to the recognised standards, and retires machines whose energy cost outweighs their use.
- How to tell
- Each machine's draw is measured at idle and under its normal load, and entered in the energy budget (domain 5).
- Power supplies are known by efficiency level. 80 PLUS sets minimum efficiencies at 10, 20, 50 and 100 per cent of load; for 230 V redundant data centre supplies, Platinum requires 88, 90, 94 and 91 per cent and Titanium 90, 94, 96 and 91 per cent (80 PLUS PSU ratings explained).
- Any UPS is specified by IEC 62040-3, the standard for stating and testing UPS performance (IEC 62040-3:2021, Uninterruptible power systems (UPS), Part 3: Method of specifying the performance and test requirements), and its batteries are installed to IEC 62485-2 for lead-acid and nickel types or IEC 62485-5 for lithium-ion (IEC 62485-2:2010, Safety requirements for secondary batteries and battery installations, Part 2: Stationary batteries, IEC 62485-5:2020, Safety requirements for secondary batteries and battery installations, Part 5: Safe operation of stationary lithium ion batteries).
- Options
- Measured figures for old and new servers. A 2012 two-socket server drew 52.7 W at idle and 250 W at full load (SPECpower_ssj2008 result: Dell PowerEdge R720 (Intel Xeon E5-2660), March 2012). A 2023 two-socket server drew 117 W at idle and 685 W at full load (SPECpower_ssj2008 result: ASUS RS720A-E12-RS12 (AMD EPYC 9754), November 2023). The overall scores were 4,836 and 36,210 operations per watt, about seven and a half times more work per unit of energy for the newer machine. These are maker-submitted benchmark runs, not field measurements.
- Idle matters. At 52.7 W continuously, the 2012 server uses about 460 kWh a year doing nothing (52.7 W times 8,760 hours). Consolidating light services onto fewer machines cuts this.
- Efficient components. ENERGY STAR states that certified servers use 30 per cent less energy than conventional models and that power management should not be disabled (ENERGY STAR Enterprise Servers). EU rules cap server idle power and set minimum active efficiency (Servers and data storage products: EU ecodesign requirements (Regulation (EU) 2019/424)).
- UPS. Covers short cuts and allows orderly shutdown. Batteries bring hazards that the IEC standards name: electricity, gas emission and electrolyte for lead-acid and nickel types; also short circuits, fire and explosion for lithium-ion (IEC 62485-2:2010, Safety requirements for secondary batteries and battery installations, Part 2: Stationary batteries, IEC 62485-5:2020, Safety requirements for secondary batteries and battery installations, Part 5: Safe operation of stationary lithium ion batteries).
- Settled, open, contested
Settled. Newer servers do much more work per watt (SPECpower_ssj2008 result: Dell PowerEdge R720 (Intel Xeon E5-2660), March 2012, SPECpower_ssj2008 result: ASUS RS720A-E12-RS12 (AMD EPYC 9754), November 2023). Stationary batteries are a recognised fire, electrical and chemical hazard with their own standards (IEC 62485-5:2020, Safety requirements for secondary batteries and battery installations, Part 5: Safe operation of stationary lithium ion batteries). Open. When to retire: one paper proposes accounting that charges more embodied carbon to new servers and reports 28 to 57 per cent carbon reductions in modelling (Advancing Environmental Sustainability in Data Centers via Carbon Depreciation Models), while another finds embodied carbon is about half of total emissions where power is mostly renewable (Sustainability in HPC: Vision and Opportunities). Neither gives a rule for a small community. Contested. Keep old machines running against replacing them: the answer depends on how clean and how scarce local electricity is.
The four stages
- Learn: idle against load, power supply efficiency (80 PLUS PSU ratings explained), and the battery hazards (IEC 62485-2:2010, Safety requirements for secondary batteries and battery installations, Part 2: Stationary batteries, IEC 62485-5:2020, Safety requirements for secondary batteries and battery installations, Part 5: Safe operation of stationary lithium ion batteries).
- Design: size the UPS to the measured load and the shutdown time needed; have a qualified electrician design the installation to the standards.
- Build: installation by a qualified person; this element gives no procedure.
- Deploy: measure draw yearly; test the UPS on a schedule; retire machines whose energy per useful task is far above a replacement's (SPECpower_ssj2008 result: Dell PowerEdge R720 (Intel Xeon E5-2660), March 2012, SPECpower_ssj2008 result: ASUS RS720A-E12-RS12 (AMD EPYC 9754), November 2023).
Resources at each stage
1 Learn
Understand
2 Design
Size and choose
- 80 PLUS PSU ratings explained Standard, S0
- ENERGY STAR Enterprise Servers Standard, S0
- Servers and data storage products: EU ecodesign requirements (Regulation (EU) 2019/424) Standard, S0
- IEC 62040-3:2021, Uninterruptible power systems (UPS), Part 3: Method of specifying the performance and test requirements Standard, S2
- IEC 62485-2:2010, Safety requirements for secondary batteries and battery installations, Part 2: Stationary batteries Standard, S3
- IEC 62485-5:2020, Safety requirements for secondary batteries and battery installations, Part 5: Safe operation of stationary lithium ion batteries Standard, S3
- SPECpower_ssj2008 result: ASUS RS720A-E12-RS12 (AMD EPYC 9754), November 2023 Dataset, S0
- SPECpower_ssj2008 result: Dell PowerEdge R720 (Intel Xeon E5-2660), March 2012 Dataset, S0
3 Build
Build or obtain
4 Deploy
Install, run and measure
- ENERGY STAR Enterprise Servers Standard, S0
- IEC 62485-2:2010, Safety requirements for secondary batteries and battery installations, Part 2: Stationary batteries Standard, S3
- IEC 62485-5:2020, Safety requirements for secondary batteries and battery installations, Part 5: Safe operation of stationary lithium ion batteries Standard, S3
What changes between 30 adults and 300 people
At 30 adults one low-power machine on a small UPS, with a laptop's own battery as an alternative (13.1). At 300 people several machines on a rack UPS with a battery installation designed to the IEC standards, a measured energy budget, and a yearly review of which machines to retire.
Reference designs
Open for contributions Designs with drawings, specifications and a bill of materials. Add to it
Parts list
Every resource that supports this element. Those marked External carry the label “External resource. Not made or verified by Public Protocol”.
The standing questions
Who can afford this: electricity over a machine's life can outweigh its price. Who does the work: a keeper measures; a qualified electrician installs. Who decides: the energy share for computing is set with the energy group (domain 5).
Environments
- Unreliable power, islands and remote places: a UPS sized to the measured load and the standards above (IEC 62040-3:2021, Uninterruptible power systems (UPS), Part 3: Method of specifying the performance and test requirements); off-grid supply is in domain 5.
- Arctic cold, hot deserts, tropical humid forest, temperate forest, high altitude, flood plains: no source found on how efficiency or UPS choice changes; battery temperature limits are in the standards, which were not read in full.
Caution. Mains wiring and battery installations can kill and can start fires. Work to the standards cited and have installations designed, installed and inspected by qualified people.
Safety
State and evidence
Drafted
An editor has written the element's text from the resources listed under it, citing them. It is checked when it is reviewed.
Evidence from a real place or system is recorded here, with what did not work. What the states mean
History
- Drafted in the release of 16 November 2026.