Element 6.12
Low-carbon structural systems and off-site building
- Sheet
- 6.12
- Chapter
- 6 Shelter and construction
- State
- Drafted
- Release
- 16 November 2026
- Editor
- Contributed by Praecise as open research
- Reviewers
- To be named at review
- Safety
- S3, as the chapter
- Licence
- CC BY-SA 4.0
- Resources
- 12
The element
- Requirement
Where the community chooses a newer or lower-carbon structural system, such as mass timber, printed walls, earth or blended cement, or a kit of parts made off site, the system has a recognised route to approval, evidence of how it behaves in fire, and a named engineer who accepts it. This element gives no structural procedure: structure is safety level S3.
- How to tell
The system appears in the code in force, or has a test-based evaluation the building official accepts, and the engineer's calculations cite it About the EN Eurocodes. For mass timber, the 2021 International Building Code added construction types IV-A, IV-B and IV-C with higher fire-resistance ratings and required noncombustible protection, allowing up to 18 storeys of Type IV-A for business and residential use Tall Wood Buildings in the 2021 IBC: Up to 18 Stories of Mass Timber. For printed construction, UL 3401 evaluates whether a fabricator's printer, material and process consistently produce elements with the integrity of the samples first tested UL 3401: Outline of Investigation for 3D Printed Building Construction. Embodied carbon is compared from a named database ICE Database (Inventory of Carbon and Energy).
- Options
Cross-laminated timber and glulam. Five real-scale, four-hour compartment fire tests with exposed timber up to twice the floor area found such rooms can burn down to embers after flashover, that two exposed walls meeting in a corner should be avoided, and that the result holds only for timber shown not to delaminate in long fires, as ANSI/APA PRG 320 (2018) requires; the tests modelled sprinklers and fire service both failing Fire safe implementation of visible mass timber in tall buildings: compartment fire testing (RISE Report 2020:94).
Open digitally cut timber kits. WikiHouse describes standard timber blocks cut to 0.1 mm precision by approved makers and assembled into a chassis on site, taking almost any insulation and cladding WikiHouse; its Skylark system covers one to three storeys under CC BY-SA 4.0 WikiHouse Skylark.
Printed walls. In earth: TECLA in Italy was printed from local raw earth in 200 hours with average power under 6 kW, and its maker reports no measured performance or code approval TECLA: 3D printed house from raw earth. In bio-based composite: a printed house was assembled from four modules in half a day and monitored through winter First 100% bio-based 3D-printed home unveiled at the University of Maine. Prototype.
Earth. Compressed stabilised earth block Compressed Stabilised Earth Block; cob, with a code appendix approved for the 2021 International Residential Code Cob Research Institute: the Cob Code.
Blended cement. Limestone calcined clay cement cuts carbon dioxide by up to 40% in existing plants LC3: Limestone Calcined Clay Cement.
Bamboo and rammed earth: no open primary source was opened in this work; the chapter is looking for their standards.
- Settled, open, contested
Settled. Exposed mass timber fire results apply only to timber that does not delaminate Fire safe implementation of visible mass timber in tall buildings: compartment fire testing (RISE Report 2020:94). New systems need a test-based evaluation before a permit UL 3401: Outline of Investigation for 3D Printed Building Construction.
Open. Long-term performance of printed earth houses TECLA: 3D printed house from raw earth; fire tests for earth block Compressed Stabilised Earth Block.
Contested. How much timber may be left exposed. The code limits exposure by type Tall Wood Buildings in the 2021 IBC: Up to 18 Stories of Mass Timber; the tests show corners of two exposed walls drive continued burning Fire safe implementation of visible mass timber in tall buildings: compartment fire testing (RISE Report 2020:94).
The four stages
Learn: fire behaviour of exposed timber Fire safe implementation of visible mass timber in tall buildings: compartment fire testing (RISE Report 2020:94); the code route Tall Wood Buildings in the 2021 IBC: Up to 18 Stories of Mass Timber. Design: the engineer designs to the code About the EN Eurocodes and compares carbon ICE Database (Inventory of Carbon and Energy); open kit files WikiHouse Skylark. Build: certified fabricators for printed and cut parts UL 3401: Outline of Investigation for 3D Printed Building Construction WikiHouse. Deploy: record products and certificates for repair and reuse.
Resources at each stage
1 Learn
Understand
- Compressed Stabilised Earth Block Guide, S3
- First 100% bio-based 3D-printed home unveiled at the University of Maine Case study, S0
- Cob Research Institute: the Cob Code Standard, S3
- About the EN Eurocodes Standard, S3
- LC3: Limestone Calcined Clay Cement Guide, S1
- Fire safe implementation of visible mass timber in tall buildings: compartment fire testing (RISE Report 2020:94) Paper, S3
- TECLA: 3D printed house from raw earth Case study, S3
- Tall Wood Buildings in the 2021 IBC: Up to 18 Stories of Mass Timber Guide, S3
2 Design
Size and choose
- Compressed Stabilised Earth Block Guide, S3
- Cob Research Institute: the Cob Code Standard, S3
- About the EN Eurocodes Standard, S3
- ICE Database (Inventory of Carbon and Energy) Dataset, S0
- Fire safe implementation of visible mass timber in tall buildings: compartment fire testing (RISE Report 2020:94) Paper, S3
- UL 3401: Outline of Investigation for 3D Printed Building Construction Standard, S3
- WikiHouse Skylark Reference design, S3
- WikiHouse Framework, S3
- Tall Wood Buildings in the 2021 IBC: Up to 18 Stories of Mass Timber Guide, S3
3 Build
Build or obtain
- Compressed Stabilised Earth Block Guide, S3
- UL 3401: Outline of Investigation for 3D Printed Building Construction Standard, S3
- WikiHouse Skylark Reference design, S3
- WikiHouse Framework, S3
What changes between 30 adults and 300 people
Thirty adults usually build one or two storeys, where kits and earth suit self-build under supervision. Three hundred people bring assembly buildings and more storeys, where fire separation, product certification and the official's acceptance become the main constraints.
Reference designs
-
Reference design
A modular timber building system for buildings of one to three storeys, published at version 1.0.
External resource. Not made or verified by Public ProtocolMaturity: Not assessedSafety S3Listed 16 November 2026
Parts list
Every resource that supports this element. Those marked External carry the label “External resource. Not made or verified by Public Protocol”.
| Resource | Type | Origin | Maturity | Safety | Licence, as stated at its source |
|---|---|---|---|---|---|
| Compressed Stabilised Earth Block | Guide | External | Established | S3 | Humanity as a whole, No rights reserved |
| First 100% bio-based 3D-printed home unveiled at the University of Maine | Case study | External | Not assessed | S0 | Not stated on the page opened |
| Cob Research Institute: the Cob Code | Standard | External | Not assessed | S3 | Not stated on the page opened |
| About the EN Eurocodes | Standard | External | Established | S3 | Not stated on the page opened |
| ICE Database (Inventory of Carbon and Energy) | Dataset | External | Established | S0 | Educational use only; must not be used for commercial applications |
| LC3: Limestone Calcined Clay Cement | Guide | External | Not assessed | S1 | Not stated on the page opened |
| Fire safe implementation of visible mass timber in tall buildings: compartment fire testing (RISE Report 2020:94) | Paper | External | Replicated | S3 | Not stated on the page opened |
| TECLA: 3D printed house from raw earth | Case study | External | Prototype | S3 | Not stated on the page opened |
| UL 3401: Outline of Investigation for 3D Printed Building Construction | Standard | External | Working | S3 | © 2026 UL LLC. All rights reserved. |
| WikiHouse Skylark | Reference design | External | Not assessed | S3 | CC BY-SA 4.0 |
| WikiHouse | Framework | External | Working | S3 | Not stated on the page opened |
| Tall Wood Buildings in the 2021 IBC: Up to 18 Stories of Mass Timber | Guide | External | Established | S3 | ©2026 WoodWorks All Rights Reserved |
Depends on, and completes
It is one of 22 elements that complete Shelter and construction.
The standing questions
Who pays for testing a material the code does not yet list. Who holds the certificates. Who decides between a local material and a listed one.
Environments
no source found.
no source found.
no source found.
no source found.
timber systems use the local resource WikiHouse; no further source found.
no source found.
see hazard-resistant building.
Other harsh settings
earthquake zones follow the earthquake code About the EN Eurocodes.
Environment profiles for these settings: Small islands and coasts; Arctic, subarctic and permafrost, including sea ice; Extreme cold; Hot deserts; Extreme heat; Tropical rainforest and humid tropics; High humidity; Temperate and boreal forests; Mountains and high altitude; River deltas and flood plains. All environments
Safety
State and evidence
Drafted
An editor has written the element's text from the resources listed under it, citing them. It is checked when it is reviewed.
Evidence from a real place or system is recorded here, with what did not work. What the states mean
History
- Drafted in the release of 16 November 2026.